NPPE Legal Terms: 27 Words That Trip Up Engineers
Law is roughly a third of the NPPE, and it is written in a vocabulary most engineers never use at work. A single unfamiliar word can make an otherwise easy question impossible. Here are 27 terms candidates most often meet for the first time on exam day, in plain language.
Forming a contract
Section IV.2 of the blueprint. Expect definition questions and short tendering scenarios.
- Invitation to treat
- An invitation for others to make offers, such as an advertisement or a general call for tenders. It is not itself an offer, so nobody can form a contract just by agreeing to it.
- Consideration
- Something of value each side gives or promises in return for the other side’s promise. It need not be money or of equal value, but a promise given for nothing in return is generally not binding.
- Contract A
- In Canadian tendering law, the preliminary contract formed between the owner and each bidder who submits a compliant bid, usually requiring a fair process and that the bid stay open for a set time. The construction contract itself is Contract B.
- Statute of frauds
- Provincial legislation requiring certain contracts, notably those about an interest in land and guarantees of someone else’s debt, to be in writing and signed to be enforceable.
Changing and ending a contract
The terms candidates most often say they had never heard before the exam.
- Waiver
- A voluntary decision, shown by words or conduct, not to insist on a contractual right you are entitled to.
- Estoppel
- A doctrine that stops a party who led the other side to believe a strict right would not be enforced from suddenly enforcing it, where that would be unfair, especially once the other side relied on the belief.
- Repudiation
- A clear signal, by words or conduct, that a party does not intend to perform the contract. Unjustified repudiation is a fundamental breach, and the other party may treat the contract as ended or insist on performance.
- Quantum meruit
- Latin for "as much as it is worth". A way to recover a reasonable amount for work actually done where no valid contract governs it, for example because the price was never agreed.
- Liquidated damages clause
- A clause fixing in advance what is payable for a specified breach, usually delay. It must be a genuine pre-estimate of the likely loss; a figure designed to punish is an unenforceable penalty.
- Indemnification clause
- A clause in which one party agrees to compensate the other for specified losses or claims, shifting that risk between them.
Torts and liability
Section IV.3. Negligence is the heart of it, and the vocabulary around it is precise.
- Tort
- A civil wrong, other than a breach of contract, for which the law gives the injured person a remedy. Negligence, nuisance, trespass and defamation are all torts.
- Standard of care
- The skill and care a reasonably competent professional would have used in the same circumstances at the time, judged against ordinary competent practice, not perfection or hindsight.
- Concurrent liability
- The principle, confirmed by the Supreme Court of Canada, that the same conduct can breach both a contract and a duty of care in tort to the same party, so a claim can be brought in either or both.
- Vicarious liability
- An employer’s liability for a tort committed by an employee acting within the scope of employment, whether or not the employer itself was at fault.
- Joint and several liability
- Where several parties contributed to the same loss, each can be made to pay the whole of it. The plaintiff collects from whoever can pay, and the defendants sort out their shares among themselves.
- Nuisance
- Unreasonable interference with someone’s use and enjoyment of their land, such as vibration, dust or contamination reaching a neighbour. Unlike negligence, it does not require proof of carelessness.
- Strict liability
- Liability that does not depend on fault. Many environmental offences work this way, which is why a demonstrated due diligence program is usually the only defence.
- Duty to warn
- A tort obligation to warn people who could be harmed by a dangerous design, product or condition you become aware of, even after your contract or involvement has ended.
- Limitation period
- The time limit for starting a lawsuit, after which the claim is barred however strong it is. In most provinces the clock starts when the loss was discovered, or reasonably should have been.
Construction and security
Section IV.9: bonds and liens, where the numbers matter.
- Bid bond
- A guarantee that a successful bidder will sign the contract. If it does not, the surety pays the owner the extra cost of the next bidder, up to the bond amount, commonly about ten percent of the bid.
- Performance bond
- A guarantee that the contractor will complete the work. After a proper default, the surety can finish the work, bring in a replacement contractor, or pay out the bond amount.
- Construction lien
- A claim registered against the property itself by anyone who supplied work or materials to it and was not paid, even without a direct contract with the owner.
- Holdback
- A percentage of each progress payment the owner must keep back, most commonly ten percent under provincial lien statutes, as a fund to satisfy liens until the deadlines to preserve them have passed.
Disputes and everything else
Sections IV.6 and IV.14, plus two terms that come up in ethics questions.
- Arbitration
- A private process in which one or more arbitrators decide a dispute. The decision is binding and enforceable, much like a court judgment.
- Mediation
- A neutral mediator helps the parties negotiate a settlement but cannot impose one. What is said in mediation is generally privileged if it fails.
- Chattels
- Movable personal property, such as equipment and materials, as opposed to real property, which is land and what is permanently attached to it.
- Due diligence
- Anticipating the reasonably foreseeable ways work could fail, putting a plan in place for each, and keeping a record that it was actually done. Evidence of it is a defence against negligence claims.
How to learn these
Definitions stick when you meet them in a scenario. Read the law chapter of the study guide, where each of these terms appears in context with worked examples, then test yourself with practice questions from Section IV. PassNPPE Pro also includes a searchable glossary of NPPE terms with examples.
Free with an account
Practise on 60 real-style NPPE questions, then sit a timed mini exam
A free account unlocks 60 practice questions weighted like the real exam, a timed mini exam (82 minutes) scored by section, and Section I of the study guide in full. Pro adds the full bank of over 1,000 questions and the 110 question simulator.